GREEN BY THE POUND - BUILDING SCHEDULE
Constructing a home over the course of three days (and two nights) requires tight planning and a well managed site. Previous to the actual three day build, the following aspects were carried out:
- Installation of the foundation and backfill.
- Rough-in of the mechanical and electrical systems.
- Installation of the underground septic, rain water and domestic water tanks.
- Installation of the basement and main floor framing and subfloor.
- Installation of the main floor deck and decking.
The following outline explains the various tasks required each day.
Day One:
- Installation of main floor walls (sips)
- Installation of roof trusses and sips panels
- Installation of doors and windows
- Installation of roofing shingles
- Installation of building paper
- Installation of interior drywall board (no taping or mudding required)
- Installation of prefinished pine at ceilings and basement and main floor
- Rough in of electrical and plumbing
Day Two:
- Installation of prefinished pine at all interior walls and partitions
- Hanging of interior doors
- Installation of door and window trims
- Installation of kitchen cabinets
Day Three:
- Installation of floor coverings
- Installation of cedar soffits
- Installation of cedar shingles at exterior walls
- Final plumbing and electrical installations
- Misc builders hardware completion
- Installation of deck railings
- General clean-up

|
|